An energy planning dilemma

The Star Online - Business·2026-11-21 08:00

MALAYSIA could be heading towards a potentially serious energy planning dilemma as it embarks on an aggressive expansion of electricity generation capacity, particularly gas-fired power plants, to meet anticipated demand from data centres (DCs).

The concern is whether the enormous amount of electricity projected for these facilities will eventually translate into actual consumption, especially in light of the US government’s tightening restrictions on advanced Nvidia chips reaching Chinese companies through third countries, including Malaysia.

If these restrictions cause some DC developers to delay, downsize or abandon their investments, Malaysia could find itself with more electricity generation capacity than it needs.

Could ordinary electricity consumers eventually be made to pay for power plants built to serve DC investments that never materialise?

The scale of Malaysia’s planned generation expansion is considerable.

Earlier this year, the government disclosed plans for up to 9,600MW of new generation capacity between 2028 and 2031, driven partly by growing electricity demand from DCs.

Under the Energy Commission’s (EC) NewGen25 programme, awards announced in February involved approximately 6,269MW of generation capacity.

……

Read full article on The Star Online - Business