Progress of ECRL project in four states reaches 65 per cent - Loke
New Straits Times·2024-05-04 18:02
HULU SELANGOR: Construction work on the East Coast Rail Link (ECRL) project in Kelantan, Terengganu, Pahang, and Selangor has reached an average of 65 per cent as of April, said Transport Minister Anthony Loke.
He said in Selangor, particularly, the project has progressed by more than 26 per cent up to last month, in line with the schedule for the preparation of the ECRL line from Gombak to Port Klang by December 2027, with operations set to commence in January 2028.